Works and Housing Minister Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024, with project coordinators and contractors to address delays plaguing the critical initiative.
"We've assessed how far the project is going and we've had several site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.
He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays.
Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval.
Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.
Addressing the Hurdles
The Minister outlined a series of measures to tackle these challenges. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up critical work areas.
On the financial front, Mr Oppong Nkrumah reassured contractors that government is actively working with Parliament to make available the outstanding funds, including the diverted $65 million.
A Race Against Time
While acknowledging the challenges, Mr Oppong Nkrumah emphasized the urgency of the completion of the GARID projects.
He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.
Latest Stories
-
Pay NABCO trainees – Mahama challenges Bawumia
4 mins -
Police ‘waiting for court date’ on Erastus’ case is a lie – Samson Anyenini
14 mins -
Sports facilities are better managed by institutions – UG Sports Director on maintenance of Legon stadium
44 mins -
Ghanaian businesses must align vision with strategy to mitigate ESG Risks – KPMG
54 mins -
MTN achieves 30% localisation of Scancom PLC
55 mins -
Attorney-General: Some lawyers sacrifice ethics for ‘cheap’ political gains
1 hour -
Bond market: Volume up by 12.45% to GH¢746m
1 hour -
Cedi records year-to-date loss of nearly 29%; one dollar going for GH¢17.10
1 hour -
‘Our priorities are wrong in Ghana’ – UG Sports Director on sports development
1 hour -
The Fourth Estate’s investigative report wins 2nd place at 2024 AIJC
2 hours -
GPL: Our fans spur us on – GoldStars head coach Frimpong Manso on unbeaten run
2 hours -
Plantain chips are breaking hearts in Africa
2 hours -
61 new architects acquire state license to practice in Ghana
3 hours -
Masloc CEO honoured as capacity building Shero of the Year
3 hours -
MPs’ Repeated Attempts to Sue the Speaker: Unintended Consequences for the 2024 Elections?
3 hours