The country's second biggest oil field, Tweneboa, Enyenra and Ntomme (TEN) project could start producing crude in commercial quantities possibly from the end of July, 2016.
This was contained in the last trading and operational update report issued by Tullow Oil, Thursday June 30, 2016.
According to the Chief Executive of Tullow Oil, Adien Heavy, the company is looking at starting production or pouring first oil within the next three to six weeks.
He adds that "After three years of hard work, I am delighted to say that the TEN Project is expected to deliver first oil within the next three to six weeks. This transformational project has remained on schedule and on budget since it began in 2013. Production at Jubilee has stabilised with a gross rate in June of around 90,000 bopd.
We have also made excellent progress on the long term solution to the turret issue, with the Jubilee Partners deciding that the optimum way forward is to spread moor the FPSO. It maintains that, they should start with a daily production of 23,000 barrels a day, till the end of this year.”
Tullow says despite the recent challenges with the FPSO, daily crude production should be put at round 90 thousand barrels till the end of this year.
The exploration firm, is also assuring investors that, it has secured, a comprehensive insurance package to take care of production challenges and losses as a result of the recent problems with the FPSO.
Read the full report below
Tullow Oil add that as previously announced, an issue with the turret bearing of the FPSO Kwame Nkrumah, identified in February 2016, has resulted in the need to implement new operating and off take procedures.
This necessitated the FPSO be shut down for an extended period in April with production resuming in early May. Since then, 18 off takes to the storage tanker have been successfully completed using a dynamically positioned shuttle tanker.
Tullow expects to continue operating the field under these new procedures for the remainder of 2016 and anticipates average gross production to be around 85,000 bopd in the second half of 2016.
Tullow and its Partners have made good progress towards establishing the best long-term solution and, based on the work undertaken over the past four months, now see converting the FPSO to a permanently spread moored facility, with off take through a new deepwater offloading buoy, as the preferred long-term solution.
The Partners are working with the Government of Ghana to seek their approval for this option. The first phase of this work will involve the installation of a stern anchoring system to replace the three heading control tugs currently in the field.
This is anticipated to be completed by the end of 2016 and will require short periods of reduced production.
Tullow then plans a second phase of work to rotate the FPSO to its optimal spread moor heading in the first half of 2017.
The work programme covering these phases, which requires Government approval, is expected to cost $100-150 million gross and it is estimated that the Jubilee FPSO will need to be shut-down for 8-12 weeks during the first half of 2017.
Upon completion of the spread mooring work programme in mid-2017, the Partners will review opportunities to improve the efficiency of offtake procedures, which may include the use of a larger dynamically positioned shuttle tanker, and seek to return production to levels seen before the turret issue occurred.
The additional gross operating expenditure of the revised procedures is currently expected to be around $115 million for 2016 and $80 million for 2017.
A deep water offloading buoy is anticipated to be installed in the first half of 2018. This will remove the need for the dynamically positioned shuttle and storage tankers and the associated operating costs. Market enquiries are currently ongoing to estimate the cost and schedule for the fabrication and installation of this buoy.
Tullow has a comprehensive package of insurances in place. This includes Hull and Machinery insurance, procured on behalf of the Joint Venture, which covers relevant operating and capital costs associated with damage to the FPSO, and Business Interruption insurance for Tullow which covers consequent loss of production and revenue. Claims under both policies have been notified to our insurers.
ON TEN
The TEN Project remains on schedule and within budget. The project is now over 96% complete and is expected to deliver first oil within the next three to six weeks.
Hook-up and commissioning of the FPSO, connecting the pre-drilled wells to the vessel via the extensive subsea infrastructure, is nearing completion. During July, the integrated start-up sequence is expected to be initiated with water injection to the Enyenra reservoir being followed by oil production. This sequence will then be repeated for the Ntomme reservoir.
A gradual ramp-up in oil production towards the FPSO capacity of 80,000 bopd is anticipated around the end of 2016 as the facilities complete performance testing and wells are brought up to optimum rates.
Tullow estimates that TEN average annualised production in 2016 will be around 23,000 bopd gross (net: 11,000 bopd). Drilling is not expected to recommence on the TEN fields until after the resolution of the Côte d’Ivoire and Ghana border dispute through the ITLOS tribunal whose decision is expected in late 2017.
The associated gas produced at TEN will be re-injected into the Ntomme reservoir gas cap until gas export begins. Gas export was planned to start 12 months after field start-up, with the Tweneboa gas reservoir coming on stream a further 12 months later.
However, options to accelerate gas export are currently being evaluated as the fabrication of the gas export facilities is ahead of schedule and is expected to be complete in late 2016, some six months early.
Latest Stories
-
Joy FM holds 2024 Prayer Summit for Peace
2 mins -
Lady sues Police and AG over assault in custody
1 hour -
Ghana’s railway sector has been revived under my leadership – Akufo-Addo
2 hours -
Next government must enforce C190 – Women Economic Dialogue Forum
2 hours -
NCCE engages party youth activists at Nandom on peaceful election
2 hours -
SSNIT engages stakeholders on its operations
2 hours -
Defilement: 19-year-old farmer jailed ten years, with hard labour
2 hours -
Bawumia to inaugurate new headquarters of Lands Commission on November 25
2 hours -
Sylvester Tetteh denies demolishing GBC staff bungalow
2 hours -
Signing of peace pact by presidential candidates slated for November 28
2 hours -
Akufo-Addo reiterates commitment to free and fair elections
2 hours -
Climate change impact poses threat to Ghana’s financial stability – BoG Governor
2 hours -
Ursula Owusu-Ekuful assures of leading NPP to victory in Ablekuma West
2 hours -
Akufo-Addo urges armed forces to maintain neutrality, professionalism
2 hours -
Driver jailed 15 years for robbery
2 hours