Government on Wednesday morning took delivery of 50 megawatts of power plants at the Kotoka International Airport as part of a first phase emergency power programme.
The plants, which were air lifted from the United States of America were purchased by the government at a cost of 26 million dollars through Marison Energy Systems and Ring Power, two energy companies based in Massachusetts and Florida respectively.
Mr Kofi Adda, Minister of Energy, Mr Kwabena T. Hammond, the Deputy Energy Minister and Mrs Dina Hammond, the Chief Director together with other energy experts met the crew of the Ukrainian Antonov Cargo Plane, which landed at 0515 hours at the Airport to take delivery of the generating plants.
Briefing the press, Mr Adda said the plants would come in 38 units, 32 of which would be lifted by air in a series of trips. The other six would arrive by sea for installation at Tema before the end of March.
He said in total, 110 megawatts of power would be installed at the Tema PSC Shipping Yard. He announced that plans were far advanced for the arrival of the other 60 megawatts plants.
Mr Adda reiterated that there would be no power interruption for two weeks from March 1 this year, after which the national load shedding programme would be reviewed.
He gave the assurance that government was working around the clock to normalise the power situation in the country within the shortest possible time.
Mr Adda said a lot had gone on with the programme, explaining that the requisite transformers and other equipment that would enable the evacuation of power after the installation has been completed.
He said installations of the generating plants commence this week at the Tema site without any delay.
Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
Latest Stories
-
Onion costs shoot up as traders lament scarcity of commodity
8 minutes -
Registration for MPs-elect to begin on December 25
12 minutes -
EC calls for stakeholders’ support to complete electoral processes
48 minutes -
Ghana Shippers Authority addresses Tema port delays, assures of efforts to resolve challenges
57 minutes -
Ensign Global College recieves Presidential Charter
1 hour -
CODEO expands post-election observation to monitor parliamentary disputes
2 hours -
Ablekuma North, Dome Kwabenya will have MPs-elect before January 7 – EC
2 hours -
Bishop Salifu Amoako involved in accident at Tesano
2 hours -
Bills Micro-Credit climax year with durbar and dinner celebration
3 hours -
Lawyer sues Wesley Girls SHS for alleged religious discrimination
3 hours -
Election: We’re not the first EC to re-collate results – Bossman Asare
3 hours -
Kofi Kinaata makes historic comeback with ‘Made in Taadi’ concert
4 hours -
It is unacceptable; EC is becoming a lawless institution – NDC on re-collation justification
4 hours -
24-hour economy in the era of digital currency adoption: Implications on economy in 2025 and beyond
4 hours -
Okaikwei Central Constituency were electoral officials cajoled into declaring wrong person – Asare Bossman
4 hours