The discomfort that comes with power crisis and the devastation caused the economy are the reasons every government must be visionary and responsive in preventing its occurrence. It is no more secret that Ghanaians are not happy about the last three years of power crises and our inability as a country to confront the challenge in spite of the lessons previous power crises have presented us with.
It is also true that in all the power crises that we went through except the 1983 one, politics have always reared its ugly head, with political actors shifting blames, and questioning the amount of generation capacity each party in government at the time added to installed generation capacity. The reality however is that every one of our constitutional governments added to the generation capacity; and made efforts to address the power crises of their times. These provide lessons on how to address the current power crisis.
Indeed our history shows that, we have successfully managed power crises in the past; and we can do it again if we muster the necessary political will and courage to take bold decisions. This paper attempts to highlight the chronology of interventions by previous governments to addressing power crises and to bring to attention lessons that can help solve the current one.
1. The 1982-85 Crisis
This crisis arose largely as a result of poor rainfall in the Volta River catchment over the 1982-84 period. This was exacerbated by the large power requirements by Valco, the aluminum Smelter which had a contractual requirement of up to 370MW at the time. The combination of the drought in the sub-region and the large power requirements imposed on the Akosombo power plant by Valco resulted in the shortage of power supply from the plant. It is to be noted that, at the time, the country depended solely on the Akosombo power plant for its electricity supplies. Togo and Benin also depended on power delivery from the Akosombo plant through a Power Supply arrangement signed in 1972.
Government Response
The strategy developed by the PNDC to deal with the crisis was to negotiate and cut off power supply to Valco with the exception of a minimum amount of power required to maintain smelting equipment, lighting, etc. Supply of power to Valco was therefore reduced from a contractual value of 370MW to 20MW.
The second measure taken by Government was to curtail power supply to residential, commercial and industrial customers. The curtailment programme was in place until 1985 when Valco resumed operations. It is to be noted however that full supply to residential customers had been restored a few months before the resumption of Valco's operations.
Follow Ups
As a result of the lessons learned during the crisis, the VRA commissioned a study to define power infrastructure investments from 1985 and beyond. This was contained in a report entitled "Ghana Generation Planning Study" issued in 1985. The Study recommended the rehabilitation of the 30MW Tema Diesel Power plant by 1986 and the construction of 250MW of thermal power plants during the period 1988 to 1996. The Tema Diesel Power plant was installed in 1961 and pre-dated the Akosombo Power plant.
While efforts may have been made, no new power plants were constructed. The Tema Diesel Power Station was rehabilitated and put into service between 1991-93 and worked at best sporadically and at high cost.
In the interim, La Cote d'lvoire had been making great strides in implementing reforms in their power sector and encouraged the advent of the operation of Independent Power Producers (IPPs). Consequently, in 1994, La Cote d'lvoire ceased to import power from Ghana, an arrangement which had been in place since 1983. Indeed, in that same year, the roles reversed and Ghana imported power from La Cote d'lvoire due to a short-term power shortage as a result of delayed rainfall into the Volta Lake.
It was not until December 1997 and January 1998 that Ghana finally had its first 220MW at the Aboadze Power plant (Takoradi 1 or T1). This was 12 clear years after the recommendation to build a thermal power plant had been made. The 110MW steam turbine was added to make it a 330MW combined cycle in 1999.
Also, in 1995, leaders of Nigeria, Ghana, Togo and Benin signed an Agreement for the development of the West African Gas Pipeline (WAGP), a project proposed by ECOWAS in 1982, based on private investment and commercial principles to supply gas security for attracting private investors into power generation; but it was not until in 2003 the four nations signed the International Project Agreement to allow for the construction of the pipeline to commence in 2005.
2. The 1998 - 2000 Crisis
This crisis arose lately as a result of a number of factors, namely, drought in the sub-region due to the El Nino climatic phenomenon and the growth in the demand for power in Ghana largely as a result of economic growth. The rate of growth of demand for power in Ghana was of the order of 10-12% per annum. While drought may have been a factor, the most significant contribution to the crisis was the delayed investment in additional thermal power plants. For 12 years after the crisis of 1983-85, the country still depended on the Akosombo/Kpong hydro plant, with some additional supply from La Cote d'Ivoire as and when there was surplus energy in that country.
Government Response
In order to address the shortage of power, the NDC Government instituted the following measures:
- A rotating load shedding programme throughout the country;
- Lease and operation of a total of 30MW Diesel power units by Aggreko plc, an international company specialized in the provision and operation of emergency power plants;
- Increased imports from La Cote d'Ivoire as and when available. This source of supply was however sporadic.
- Negotiated and shut the Valco Smelter down, reducing its energy consumption from 245MW to 20MW. The Government compensated Valco for the energy "bought back".
Notably, two other transactions to lease thermal plants to ameliorate the crisis ran into commercial and contractual disputes. In the case of Faroe Atlantic, the 70MW plant was not delivered and resulted in a commercial dispute which went all the way to the Supreme Court. The other transaction involved SIIF which delivered a 32MW power plant long after the power crisis was over in 2001/2002. The legal issues were subsequently settled between the Government and the owners of the power plant.
The crisis subsisted until 2000.
Follow Ups
The Government arranged for the expansion of the Aboadze Power Complex with the phased addition of a 330MW Combined Cycle power plant. The Government policy at the time was to use private capital in whole or part in developing and investing in power generating plants.
The first phase of the expansion involved the construction of 220MW Gas turbines by the Takoradi International Company (TICo), also called Takoradi 2 (or T2), a joint Venture (JV) between CMS Generation of the USA and the VRA. Subsequently, CMS' stake in the JV was taken over by TAQA of Abu Dhabi. The gas turbines were commissioned in February and September 2000 respectively. The additional 110MW steam to form the combined cycle block is however currently under construction.
3. The 2006-2007 Crisis
The major reason for the crisis was the poor rainfall resulting in reduced inflow into the Volta Lake and the non-availability of sufficient reliable thermal power generators at the Aboadze power plant to complement the reduced generation from Akosombo/Kpong. Notably, the Aboadze plant had suffered a prolonged outage due to a fault.
Government Response
The NPP Government instituted the following measures:
- Procurement, installation and operation of 126 MW Diesel generating units;
- Lease of 25MW of Diesel units by TransTema Limited;
- Facilitated the procurement and installation of the 80MW Mine Reserve Plant. This was a plant procured by a number of mining Companies to be operated by the VRA. The understanding was that in the event of any future load shedding, they will have the first call on the output from the plant.
- Procurement of 6 million compact fluorescent lamps to reduce the lighting load. The energy savings from this intervention was 125MW.
- The Government bought Valco and freeing up of about 370MW of power hitherto available to Valco;
- Institution of a rotating load shedding programme throughout the country. The crisis subsisted from August 2006 to September 2007.
Follow Ups
Following the crisis, the Government implemented projects aimed at addressing the medium to long-term power generation investments in the country. They included:
- Acceleration of the construction of the 126MW Tema thermal 1 Power Plant (TT1PP) started in 2006. This project was completed in 2008.
- Procurement and construction of the 50MW Tema Thermal 2 Power Plant (TT2PP). This project was completed in 2009.
- Procurement and construction of 220MW Kpone thermal Power plant. The turbines were delivered in 2008 and the civil works were 20 % complete in December 2008 and was due for operation in June 2009. The project was subsequently discontinued by the new Government. Work has recently re-started and is due for completion in mid-2015.
- The development and construction of the 400MW Bui Hydroelectric Power plant. Work started in August 2007.
- Payment of Ghana's share of the cost of WAGP project to allow for the construction of the pipeline to commence in 2005. First gas was delivered to Ghana in December 2008.
- Development and financing of the 132MW Takoradi 3 Power plant (T3) at Aboadze. The project was subsequently implemented by the new Government in 2009.
In addition the following private sector (IPP) projects were facilitated.
- 200MW Sunon Asogli Power plant
- 126MW Osonor power plant. The plant was subsequently acquired by SSNIT and renamed CENIT power plant.
4. The Current Crisis - 2012 - 2015
The current crisis commenced in August 2012 when a fault on the WAGP pipeline resulted in the cut-off of natural gas supply from Nigeria to the thermal power plants in Ghana. Subsequently a number of reasons have been adduced as the cause of the power shortage including:
- Poor rainfall into the Volta Lake, thus reducing power generation from Akosombo/Kpong;
- Maintenance work on the thermal plants;
- Lack of financing for fuel procurement, etc.
Notwithstanding the reasons above,
- The Volta Lake was full in 2011. If it had been properly managed, it should not be empty after two less than average rainy seasons. The reason for the low level of the Lake is that the lack of financing by Government forced the management of VRA to take more power (30% more) than is considered technically acceptable from the Akosombo power plant over the last two years. That is, the plant was operated in a risky manner. Also, lack of ECG payments did not allow VRA sufficient revenues to buy crude oil on its own.
- In spite of the disruptions in natural gas supply, Nigeria delivered an average of 60- 65MMscf/day in both 2013 and 2014. This was 50% of their contractual obligation. What they failed to supply is the requirement for 200MW of thermal generation. So in effect, the "Nigeria gas Effect" contributes to only 200MW out of the 650MW that is being shed.
- Jubilee gas which has been delayed for 3 years (due to inconsistency in the implementation of a previously planned investment framework) is now available but half of the total gas supplies is stranded in Takoradi and cannot be used in the Tema thermal plants due to lack of interconnection between the Atuabo Gas Pipeline and the West African Gas Pipeline which extends to Tema.
These factors have had combined effects on the current power crisis.
What Government must do?
a. Short-term Measures
In the short-term, the government must take the following measures.
- Regroup and refurbish the Diesel units procured for the last power crisis in 2006. At least 70-80MW can be recovered instead of exporting them to Sierra Leone as being speculated. This is important because, with current low oil prices, they are not expensive to run. Government must also remove taxes, levies, VAT, etc, to have the full effect of US$50 per barrel oil prices. Generation cost on these plants is low. These can be used to serve industry in Tema.
- Accelerate the completion of the 220MW Kpone thermal Power plant and secure fuel supply.
- Accelerate completion of the T2 plant expansion by 110MW to allow for full output of 330MW.
- Arrange for funding of fuel for TT1PP and CENIT Power plants (220MW).
- Procure 150-200MW short-term generation.
These measures will make available about 800MW of generation capacity (from existing and new capacity), more than required to neutralize the 650MW power deficit currently being shed in the country. In this case, we will need only one power ship (225MW) and not two or three as currently being negotiated by Government at huge cost to the state.
a. Long-term Measures
In the long-term, Government must incentivize accelerated private sector investments in power generation through realistic tariffs and fuel security particularly from indigenous gas sources and Liquefied Natural Gas (LNG) projects. This should take into consideration the annual growth in demand for power at 12% and a reserve margin of 25%. A number of Power Purchase Agreements have already been signed but have not yet translated into generation capacity due to delays in reaching financial closures.
Government must also pay its debts to the Electricity Company of Ghana (ECG) and stop further accumulation of new debts to improve on the financial strength of the company thereby repositioning it as a credible off-taker. This is necessary to reassure investors that ECG can pay for the power sold to it.
However, while such investments are necessary, the current experience shows that the process for reaching these power deals is not transparent and predictable. The effect of this is that substandard plants are brought in with low fuel efficiency as well as low availability factor.
We must develop standards that define the type and quality of generation plants we need, setting levels for fuel efficiency, availability factors, and generation costs. Apart from increasing the availability of the plants, this will also prevent the current situation where different plants have different tariffs because some have relatively higher generation costs.
We must also set realistic timelines for bringing new generation capacity on stream to allow for industrial development planning. This should also take into consideration the need to rehabilitate and expand the transmission and distribution network since increasing generation capacity without expansion in the transmission network brings on us another challenge of distributing generated power.
Latest Stories
-
Mahama’s administration to consider opening Ghana’s Mission in Budapest
10 seconds -
GEPA commits to building robust systems that empower MSMEs
3 minutes -
Twifo Atti-Morkwa poultry farmers in distress due to high cost of feed
5 minutes -
Central Region PURC assures residents of constant water, power supply during yuletide
6 minutes -
Election victory not licence to misbehave – Police to youth
8 minutes -
GPL 2024/2025: Nations thrash struggling Legon Cities
10 minutes -
Electoral offences have no expiry date, accountability is inevitable – Fifi Kwetey
11 minutes -
Ghanaians to enjoy reliable electricity this Christmas – ECG promises
18 minutes -
Police deny reports of election-related violence in Nsawam Adoagyiri
21 minutes -
‘We’re not brothers; we’ll show you where power lies’ – Dafeamekpor to Afenyo-Markin
25 minutes -
EPA says lead-based paints are dangerous to health, calls for safer alternatives
2 hours -
Queenmother calls on President-elect Mahama to appoint more women in his government
4 hours -
Atletico Madrid beat Barcelona to go top of La Liga
5 hours -
Usyk breaks Fury’s heart with points win in rematch
5 hours -
Ghana-Russia Centre to run Russian language courses in Ghana
10 hours