President Nana Akufo-Addo has inspected ongoing work on the construction of the Kumasi International Airport, which, according to the contractor, is currently 77% complete, and is expected to be completed in June 2022.
President Akufo-Addo visited the site of the construction on Friday when he commenced his four-day working visit to the Ashanti Region, as part of his annual working visits to all the regions of the country.
On June 6, 2018, the President cut the sod for the commencement of work on Phase Two of the Kumasi Airport Project, where he indicated that “the expansion of this airport is a critical part of government’s vision to expand the frontiers of the aviation industry in the country and to realise the dream of making Ghana an aviation hub in West Africa.”
Inspecting work on the site, the President was told that the terminal building was 88% complete, the road network 93% complete, the Apron 89% complete, with the air traffic control and rescue and firefighting services 53% complete.
The scope of work includes the extension of existing runway pavement from 1,981 metres to 2,320 metres, the construction of a new taxi link and apron, two new apron parking stands, aeronautical ground lighting systems, the design and building of a terminal with the capacity to handle 800,000 passengers per annum, an 11 MW substation, as well the provision of new bulk utility (electricity, water, sewage treatment system, internet etc.) services, independent of the existing utility services for the existing airport facilities.
Phase three of the project involves the construction of the air traffic control building, a fire building station, as well as the expansion of the existing runway pavement. The construction of the fuel farm is to be funded by GOIL.
With the project being constructed by Messrs. Contracta Construction UK Limited, the total project sum is €124.9 million, with financing from Santander, Deutche Bank, and UKEF.
President Akufo-Addo expressed satisfaction with the progress of work undertaken so far, and charged the Ministry of Transport as well as the Contractor to ensure that the October 2022 deadline for completion is met.
Latest Stories
-
Bonmati named Fifa Best women’s Player of the Year
11 seconds -
Vinicius Jr named Fifa Best men’s Player of the Year
4 minutes -
Parliament pays tribute to Clement Ike Quartey ahead of final funeral rites
18 minutes -
Bawumia to grace Parliament’s Festival of Nine Lessons and Carols
41 minutes -
Mahama outlines infrastructure investment for economic growth
42 minutes -
Keta Beach: Africa’s Golden Gem of Serenity and Beauty
43 minutes -
Esther Smith reiterates excitement about her return to the music scene
56 minutes -
NCDs, globally, cause more than 41 million deaths annually – GhNCDA
58 minutes -
Mahama promises to work with religious bodies to expand healthcare services
2 hours -
Kosmos Energy walks away from Tullow Oil acquisition
2 hours -
Ghana-Russia Centre to donate essential items to children in Pakro-Zongo ahead of christmas
2 hours -
South Tongu: EPA holds health walk to raise awareness on environmental issues
2 hours -
Joe Mettle, Perez Musik, Efya, and Kidi billed for 2024 MTN Festival of Nine Lessons and Carols
2 hours -
Serene Insurance honours its agents at maiden Awards Night
2 hours -
Chief Imams congratulate Mahama, NDC for electoral victory
2 hours