The board and management of the Komfo Anokye Teaching Hospital (KATH) in Kumasi have expressed worry over the continued delay in the completion of works on a sickle cell and blood center project for the hospital.
Construction works on the project, which is being sponsored by the Sickle Cell Foundation of Ghana (SCFG) with funding from the Ghana National Petroleum Corporation (GNPC), have come to a halt for more than two years.
The project was to be completed in May 2019 but had to be extended for one year to May 2020.
So far, the first fixing of the plumbing and electrical works have been completed and the building of the basement structure and ground floor has also been finished.
However, further works on the project have been aborted because the contractor had not been paid since August 2020 and at the end of the year 2021, the project was still behind schedule.
This came to light when the Chief Executive Officer of KATH, Dr Oheneba Owusu-Danso, led members of the KATH Board to visit some of the hospital projects under construction.
The visit was to allow the board members to acquaint themselves with the progress of work on the projects and the challenges facing the contractors.
Nana Asibey Opoku, Consultant to the project, told the team that since August 2020, no payment had been made to the contractors, thus accounting for the stalling of the project.
He said the Foundation had lobbied the Asantehene, Otumfuo Osei Tutu II, to press on the GNPC to release funds for the completion of the project.
The GNPC, through the Asantehene in 2016, presented a cheque for $4.5 million to the Sickle Cell Foundation for the construction, tooling, and training of the personnel for the first-ever Sickle Cell and Blood Centre in Ghana at KATH.
Members of the KATH Board who were visibly worried about the situation expressed grave concerns about the delay of the project and said it could affect the cost of the project and further delay its completion.
The board appealed to the GNPC to honour its pledge and pay the contractor to enable them to complete the project.
When completed, the center will serve as a one-stop for the management of all sickle cell cases and blood transfusion-related services for the northern half of the country.
Latest Stories
-
The former illegal miner who became valedictorian: Eliasu Yahaya Bansi’s KNUST journey
8 mins -
Prof Opoku-Agyemang slams gov’t over supply of ‘expired’ rice to Senior High Schools
13 mins -
‘Expired rice’: FDA fines Lamens Investments GH¢100k for regulatory violations
17 mins -
No student has been served unwholesome meals – Nana Boakye
31 mins -
Galamsey has left our river deities powerless – Fetish Priest laments
45 mins -
It was unfair to destroy Leslie’s Fantasy Dome – Okraku-Mantey
49 mins -
Expired rice scandal: We won’t jeopardize people’s health or safety for any reason – FDA
54 mins -
UniMAC to host public forum on democracy and communication
1 hour -
Expired Rice Scandal: Ablakwa slams Lamens Company for “Criminal” acts
1 hour -
Avoid the use of vituperative expressions in your campaigns – NCCE
2 hours -
No petroleum revenue allotment to industrialisation in first half of 2024 – PIAC report
2 hours -
Baba Sadiq motivated me to vie for MP position – Okraku-Mantey
2 hours -
“Black Stars failure to qualify for AFCON 2025 a big blow” – Ibrahim Tanko
2 hours -
NPP’s campaign is going very well – Nana Akomea
2 hours -
Employees must file annual income tax returns – Ghana Revenue Authority
3 hours