The Minority in Parliament has raised concerns about the significant cost escalation of the Flower Pot Interchange project in Accra.
Initially awarded in November 2016 for GH¢ 69.5 million, the project’s cost was revised to GH¢ 147 million in 2017 and now nears GH¢ 1 billion.
Minority Chief Whip and Adaklu MP, Governs Kwame Agbodza, has questioned the rationale behind the steep increase, suggesting the government owes the public a detailed explanation.
He called for transparency regarding the factors contributing to the escalation.
“Unless the scope has completely changed, it doesn’t make sense for the cost to double or more,” Mr. Agbodza said in an interview on Joy FM’s MiddayNews on Tuesday, November 19.
“Is it the 150 meters added that is changing the cost from GH¢ 69 million to currently GH¢ 700 million? Is it the cost of exchange rate, and materials? Somebody must explain these things.
“This is at the time that President Akufo-Addo and Dr Bawumia when in opposition in 2016 turned themselves into political quantity surveyors knowing the price of everything and complaining about the price of Kasoa Interchange. They must come out to explain how a GH¢69 million cedis project has turned into almost GH¢1 billion at the time of completion,” he said
Mr Agbodza urged the government to address these concerns during the project’s commissioning, emphasizing the need for accountability on potential future cost variations as the project nears completion.
“What is a bit surprising to me is the level of unexplained variation. In September this year, four variation orders were changing the project to almost GH¢700 million.
“If you listen to the Director of Urban Roads, the project is not yet fully done so the point is if it is GH¢700 million cedis currently, what exactly is it going to be at the final cost of construction?” he asked.
Latest Stories
-
NDC government will fairly share the national cake – Prof Opoku-Agyemang
4 mins -
Nigeria intercepts 50,000 tramadol pills smuggled from Ghana
5 mins -
Three power plants to shut down if… – IPP CEO
31 mins -
North Dayi to get transit quarters to boost local economy
42 mins -
Political, Economic, and Technological analysis
56 mins -
Ghana will no longer be held back by energy shortages of the past – Akufo-Addo assures
1 hour -
We are aware of allegations surrounding operations of Development Bank Ghana – World Bank
1 hour -
AFCON 2025Q: Cameroon complete unbeaten qualifying run, Kenya and Namibia bow out
2 hours -
AFCON 2025Q: Tanzania defeats Guinea to secure AFCON ticket
2 hours -
Ghana embarks on polio vaccination campaign amid rising cholera cases
2 hours -
Election 2024: NCCE urges political parties to foster peaceful campaigns
2 hours -
We have disappointed the country – Black Stars team manager, Ameenu Shardow
2 hours -
‘I never thought of playing for Germany even though I was born there’ – Otto Addo
2 hours -
Samira Bawumia launches second literature anthology, ‘We Move: Ghanaian Dream in Motion’
2 hours -
Jobberman CEO charges employers to create culture of excellence in today’s competitive market
3 hours