The government of Ghana has been advised to consider the termination of the contract agreement between the National Youth Authority and New Case Construction Limited, for the construction of the Azumah Nelson Sports Complex.
In its latest audit, government's Entity Tender Committee reportedly discovered several breaches of the contract agreement, by New Case Construction Limited.
Speaking exclusively to JoySports, Chief Executive Officer of the NYA, Pius Enam Hadzide said the Authority was considering the recommendation.
''The Entity Tender Committee at its last meeting, advised that we consider the termination of the agreement because the contractor has no done some of the works that we believe should have been done by now.''
The Azumah Nelson Sports Complex, like all ten Youth Resource Centers across the country, was supposed to be completed within nine months of commissioning.
In August 2020, the facility was declared 78% complete by the project engineer, Paul Atanga.
Work was progressing steadily in 2019 until monies ceased coming
''We are 78% through with the work. When we started this work, there were unforeseen circumstances that we met, and as engineers when we meet a problem, we solve them before moving on.
''There is a drain that passes through the facility that discharges water from the Kaneshie township all the way to Odawna. It was passing through our VIP area, so we had to divert it so we don’t flood the industrial area.
''So that has been cleared. We are confident that we will finish the remaining 22% in the next few months, he told reporters during a site inspection.
However, work stalled on the project shortly after, following government's inability to pay contractors working on all ten Youth Resource Centers.
The NYA contends that it does not owe New Case Construction Limited, who are responsible for the project.
''So we are considering the termination (of the contract with New Case Construction Limited). And no, we do not owe them.'' he told JoySports.
Meanwhile, construction works on the nine other facilities have ceased due to a lack of funds.
The District Assembly's Common Fund have since July 2022, refused to release funds to the NYA.
Since the NYA is mainly funded by 5% of the District Assembly's Common Fund, the current situation has made it impossible to finance the project.
The $4million facility is expected to have an ICT Center, tennis and basketball courts, a FIFA standard sized pitch with seating capacity of 5,000 spectators and boxing gyms.
Latest Stories
-
Inlaks strengthens leadership team with key appointments to drive growth across sub-Saharan Africa
11 minutes -
Green Financing: What Ghana’s Eco-startups need to know
16 minutes -
CHAN Qualifiers: Amoah confident of beating Nigeria
16 minutes -
Governments deprioritising health spending – WHO
23 minutes -
Lordina Foundation brings Christmas joy to orphans
23 minutes -
Yvonne Chaka Chaka to headline ‘The African Festival’ this December
24 minutes -
Nigerian man promised pardon after 10 years on death row for stealing hens
27 minutes -
MGA Foundation deepens support for Potter’s Village
48 minutes -
Galamsey: One dead, 3 injured as pit collapses at Nkonteng
1 hour -
Man, 54, charged for beating wife to death with iron rod
1 hour -
MedDropBox donates to UG Medical Centre
2 hours -
Afenyo-Markin urges patience for incoming government
2 hours -
Case challenging Anti-LGBTQ bill constitutionally was premature – Foh Amoaning
2 hours -
Fifi Kwetey: An unstoppable political maestro of our time
2 hours -
Volta Regional ECG Manager assures residents of a bright Christmas
2 hours