Works and Housing Minister Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024, with project coordinators and contractors to address delays plaguing the critical initiative.
"We've assessed how far the project is going and we've had several site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.
He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays.
Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval.
Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.
Addressing the Hurdles
The Minister outlined a series of measures to tackle these challenges. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up critical work areas.
On the financial front, Mr Oppong Nkrumah reassured contractors that government is actively working with Parliament to make available the outstanding funds, including the diverted $65 million.
A Race Against Time
While acknowledging the challenges, Mr Oppong Nkrumah emphasized the urgency of the completion of the GARID projects.
He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.
Latest Stories
-
Ghanaian youth unaware of their right to hold politicians accountable – Youth Bridge Foundation
10 mins -
Judge delays Trump sentencing for a third time
26 mins -
2024 WAFCON: Ghana drawn against defending champions South Africa in Group C
55 mins -
Photos from DW-JoyNews street debate on ‘galamsey’
2 hours -
Mimmy Yeboah: Blending heritage with global sophistication, confidence redefined through couture
2 hours -
100 Most Influential People Awards 2024: Brain Hill International School’s Director Mary Anane Awuku honoured
2 hours -
Akufo-Addo commissions 97-km Tema-Mpakadan railway line
2 hours -
Majority requests recall of Parliament
3 hours -
Kanzlsperger and Professor Quartey support WAFA with medical Donation
3 hours -
Gideon Boako donates 10 industrial sewing machines to Yamfo Technical Institute
3 hours -
‘Golden Boy’ Abdul Karim Razak honored at WAFU-B general assembly
3 hours -
Buipewura Jinapor secures Vice Presidential position in National House of Chiefs with record votes
3 hours -
2024 election: I want results to come out like ‘milk and honey’ – Toobu
3 hours -
Ghana’s Henry Bukari hands over chairmanship of ECOWAS Brown Card Council of Bureaux
3 hours -
Residents of Dome-Kwabenya on edge ahead of December elections
4 hours