Works on the 50-megawatt solar power plant being constructed at Galgu in the Yendi Municipality of the Northern Region, is expected to be completed by November this year.
The construction of the $59 million project, being spearheaded by the Bui Power Authority, began in September 2023, and it would enhance energy security and reliability in the country.
The project that involved the construction of a powerhouse, workers’ accommodation, a five-kilometre access road and other auxiliary works, is currently about 75 per cent complete.
Dr Samuel Kofi Dzamesi, Chief Executive Officer of Bui Power Authority, who led a delegation to inspect the progress of work on the project at Galgu, said it formed part of the government’s commitment to transform the country’s energy sector.
The delegation included Members of Parliament, officials from the Ministry of Energy, Ghana Grid Company Limited and traditional authorities.
Dr Dzamesi said the First Sky Group was the financier and contractor of the project under an engineering, procurement, construction, and financing agreement.
He said: “After completion, we will generate power, sell it, and pay the First Sky Group for eight years.”
“The 140 acres of land provided by the Overlord of Dagbon is sufficient for 100 megawatts. We hope to enter another agreement with the contractor for an additional 50 megawatts after completing this phase,” he added.
Mr Eric Seddy Kutortse, Executive Chairman of First Sky Group, commended the Bui Power Authority for bringing the project to life and the opportunity given to his company to contribute to the nation’s future and lead the charge for sustainable development.
He gave the assurance that the project would be ready for inauguration by November, this year if everything went according to plan.
Mr Emmanuel Adumua-Bossmam, a Deputy Chief of Staff at the Office of the President, said the project was a catalyst for development and would help in creating jobs.
Mr Owuraku Aidoo, Chairman of the Parliamentary Select Committee on Energy, said the project demonstrated Bui Power Authority’s commitment to supporting the country’s renewable energy sector.
Alhaji Salifu Saeed, a Board Member of Bui Power Authority, said the project was evidence of the peace in the Dagbon Traditional Area and called on the people to sustain the peace in the area.
Naa Dr Jacob Mahama, Chief of Zangbalun, who spoke on behalf of Ya-Na Abukari (II), Overlord of Dagbon, lauded the project and said “Solar energy will enable our communities to thrive, foster economic growth and development. So, we are all prepared to give our best in ways that will promote the completion of the project on schedule.”
Latest Stories
-
Ghana Poultry Network honoured at Ghana Strategic Customer Relationship Conference & Awards
2 minutes -
Gov’t has introduced 4 new taxes, abolished 3, not 6 taxes – Gideon Boako
16 minutes -
Turkish company Synergy to produce solar panels in Ghana
23 minutes -
Kwaafo-Kwahu hemaa Nana Akosua Asantewaa congratulates new Kwahu chief on his inauguration
30 minutes -
Kpando Senior High School PTA hands over 4 projects to management
37 minutes -
2025 budget a breath of fresh air but… – Franklin Cudjoe
60 minutes -
Finance Minister concedes significant GDP growth, improved debt to GDP ratio under NPP government
1 hour -
AI4SD launches innovation and startup training Programme in Ghana
2 hours -
Rainbow nations challenge tennis tournament returns for fourth edition in Accra
2 hours -
2025 Budget: Gov’t allocates GH¢200m to support coastal erosion victims
2 hours -
From label loyalty to freedom’s fiasco: The cautionary tale of Kuami Eugene
2 hours -
Volta Region: Women leaders call for greater involvement and mentorship
2 hours -
Assembly members thank Mahama for allocating funds to pay them monthly allowance
3 hours -
Affirmative Action Law: Parliament committed to increasing women participation in governance to 45% – MP
3 hours -
KMA launches phase two City Cancer Challenge to accelerate cancer care solutions
3 hours